        | 16. | 2024-0910 RECEIVE AND FILE status report on the Program Management Quarterly Change Report. None | View | Download | 
      
  
      
      
        | 17. | 2024-0926 INCREASE the Life-of-Project (LOP) budget for the Regional Connector Transit Corridor Project (Project) by $39,000,000 from $1,755,840,570 to $1,794,840,570 to fully resolve claims and complete ... Adopted | View | Download | 
      
  
      
      
        | 18. | 2024-0527 INCREASE the Life-of-Project (LOP) budget by $99,730,000 for the Division 20 Portal Widening Turnback Facility (Project) from $956,749,577 to $1,056,479,577 using the fund sources as summarized ... Adopted | View | Download | 
      
  
      
      
        | 19. | 2024-0857 AUTHORIZE the Chief Executive Officer to:
A.	ESTABLISH the I-105 ExpressLanes Project 475004 Life-of-Project (LOP) Budget by increasing the existing Preconstruction Budget and by establishing ... Adopted | View | Download | 
      
  
      
      
        | 20. | 2024-0993 AUTHORIZE execution of Amendment No. 4 to the Funding Agreement between the Metro Gold Line Foothill Extension Construction Authority ("Authority") and the Los Angeles County Metropolitan ... Approved | View | Download | 
      
  
      
      
        | 21. | 2024-0553 RECEIVE the quarterly oral report on the status of the Caltrans construction projects. None | View | Download | 
      
  
      
      
        | 22. | 2024-0531 RECEIVE AND FILE the Program Management Project Status Report. None | View | Download | 
      
  
      
      