Thu 7/16/2015
9:00 a.m.
One Gateway Plaza, Los Angeles, CA 90012,
3rd Floor, Metro Board Room
During the meeting
By phone:You may join the public comment participation call 5 minutes prior to the start of the meeting.
Dial-in: 202-735-3323
English Access Code: 5647249#
Spanish Access Code: 7292892#
To give public comment on an item, enter #2 (pound two) when that item is taken up by the Board.
Need assistance with your audio? Please dial 888-796-6118.
When you call in to comment, you will be able to hear the live stream of the meeting while you wait to comment. If you are also listening to the meeting on another device, please lower the volume on the second device to avoid feedback and ensure you can be heard clearly.
To use a link in the PDF below, hold the CTRL button on your keyboard when clicking the link.
Click "View" to go to the board report detail page. Click "Download" to download a copy of board report and its attachments.
29. | 2015-1059 RECEIVE report of the Chief Executive Officer. Received | View | Download |
31. | 2015-0711 RECEIVE AND FILE status report on the Project Labor Agreement and Construction Careers Policy programs on the Crenshaw/LAX Transit Corridor and Regional Connector Transit Corridor projects for ... Received | View | Download |
32. | 2015-0882 RECEIVE AND FILE the monthly report on Transit Program Project Budget & Schedule Status. Received | View | Download |
33. | 2015-1057 RECEIVE report by the Caltrans District Director on Delivery of Projects on I-5. Received | View | Download |
34. | 2015-0955 CONSTRUCTION COMMITTEE RECOMMENDED (5-0) authorizing the Chief Executive Officer to amend the FY16 budget to add 33 non-contract full-time equivalent (FTE) positions: A. 18 non-contract FTE ... Approved | View | Download |
35. | 2015-0958 CONSTRUCTION COMMITTEE RECOMMENDED (5-0) authorizing: A. an increase to the total contract value for Contract No. MC069, with Stantec Consulting, Inc., to provide Construction Management ... Approved | View | Download |
36. | 2015-0960 CONSTRUCTION COMMITTEE RECOMMENDED (5-0) authorizing the Chief Executive Officer to execute Contract Modification No. 3 to Contract No. MC070, to ARCADIS U.S., Inc., to continue providing ... Approved | View | Download |
37. | 2015-0961 CONSTRUCTION COMMITTEE RECOMMENDED (5-0) authorizing the Chief Executive Officer (CEO) to execute Change Modification No. 2 to Contract No. MC071, Westside Extension Support Team (WEST), to ... Approved | View | Download |
38. | 2015-0848 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION: A. authorizing an increase to the total authorized funding for Contract No. PS100800-2641 with MARRS Services, Inc., for pending and ... Approved | View | Download |
39. | 2015-0215 CONSTRUCTION COMMITTEE RECOMMENDED (5-0): A. finding that awarding design-build contracts pursuant to Public Utilities Code Section 130242 (a) will achieve private sector efficiencies in the ... Approved | View | Download |
40. | 2015-0223 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the Chief Executive Officer to award a 28 month firm fixed price contract, under Invitation for Bid No. C1078, with Clark ... Approved | View | Download |
41. | 2015-0224 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the Chief Executive Officer to award and execute a five year contract, Contract No. PS84203243, with Cumming Construction ... Approved | View | Download |
42. | 2015-0542 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the Chief Executive Officer to award and execute a five year contract, Contract No. PS84203274, with Kleinfelder, Inc. for ... Approved | View | Download |
43. | 2015-0722 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION: A. authorizing a Contract Modification No. 40 (a.k.a. Contract Change Order, CCO 40) by Caltrans for Segment 3 construction contract of ... Approved | View | Download |
44. | 2015-0849 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION approving an increase in the Contract Modification Authority (CMA) to Contract No. PS0933432406A with STV Incorporated (STV) in the amount ... Approved | View | Download |
45. | 2015-0952 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION: A. authorizing the Chief Executive Officer (CEO) to continue issuing task orders within the previously Board approved total contract ... Approved | View | Download |
46. | 2015-0586 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION approving an increase in the Contract Modification Authority (CMA) to Contract No. OP33402180 with Maintenance Design Group (MDG) in the ... Approved | View | Download |
47. | 2015-0851 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the Chief Executive Officer (CEO) to execute Contract Modification No. 39 to Contract No. E0117 with Hatch Mott MacDonald ... Approved | View | Download |
48. | 2015-0957 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the CEO to execute Contract Modification No. 22 to Contract No. E0119 with The Connector Partnership Joint Venture (CPJV) Inc. ... Approved | View | Download |
49. | 2015-1069 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION authorizing the Chief Executive Officer to execute a cost-plus-fixed-fee Contract No. PS2415-3412 with STV, Inc. for the Brighton to ... Approved | View | Download |
50. | 2015-0805 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION: A. adopting Life-of-Project (LOP) budget for Project 205104 (Metro Blue Line (MBL) Pedestrian Active Grade Crossing Improvements ... Approved | View | Download |
75. | 2015-0577 CONSTRUCTION COMMITTEE FORWARDED WITHOUT RECOMMENDATION amending the FY 16 Budget to add $800,000 to Project 405556 Systemwide Planning in Cost Center 4330, Countywide Planning and Development to ... Approved | View | Download |
51. | 2015-0844 RECEIVE AND FILE the monthly report on Crenshaw/LAX Safety. Active | View | Download |
52. | 2015-0886 RECEIVE AND FILE Engineering and Construction Executive Director’s report. Active | View | Download |